某项目制定的开发计划中定义了3个任务,其中任务A首先开始,且需要3周完成,任务周完B必须在任务A启动1周后开始,且需要2周完成,任务C必须在任务A后才能开始,且需要完成2周完成。该项目的进度安排可用下面的甘特图 ( ) 来描述。
A. A
B. B
C. C
D. D
软题库参考答案:D(仅供参考)
软题库解析:正在加载....
你可能感兴趣的试题
The purpose of the requirements definition phase is to produce a clear, complete, consistent, and testable (1) of the technical requirements for the software product.
During the requirements definition phase, the requirements definition team uses an iterative process to expand a broad statement of the system requirements into a complete and detailed specification of each function that the software must perform and each (2) that it must meet.The starting point is
交换机命令show interfaces type0/port_# switchport|trunk用于显示中继连接的配置情况,下面是显示例子:
2950#show interface fastEthernet0/1 switchport
Name: fa0/1
Switchport: Enabled
Administrative mode: trunk
Operational Mode: trunk
Administrative Trunking Encapsulation: dot1q
Operational Trunking Encapsulation: dot1q
egotiation of Trunking: disabled
Access Mode VLAN: 0((inactive))
Trunking Native Mode VLAN: 1(default)
Trunking VLANs Enabled: all
Trunking VLANs
在Windows Server 2003上启用IIS 6.0提供web服务,创建一个web站点并将主页文件index.asp拷贝到该web站点的主目录下。在客户机的浏览器地址栏内输入网站的域名后提示没有权限访问网站,则可能的原因是 ( ) 。
A、没有重新启动web站点。
B、没有在浏览器上指定该web站点的服务端口80。
C、没有将index.asp添加到该web站点的默认启动文档中。
D、客户机安装的不是Windows操作系统。