Software engineers apply the principles of software engineering to the design, development, ( ),testing, and evaluation of the software and systems that make computers or anything containing software work.
A. Requirement
B. construction
C. service
D. maintenance

查看答案

软题库参考答案:D(仅供参考)

软题库解析:正在加载....

你可能感兴趣的试题

28题:项目具有临时性、独特性与渐进明细的特点,其中临时性指()。
A、项目的工期短
B、每个项目都有明确的开始与结束时间
C、项目的成果性目标是逐步完成的
D、项目经理可以随时取消项目
71题:

The project manager must maintain an effective communication link with the customer’s satisfaction with the progress of the project. The projectmanager maintains this link through(  ).
A.Periodic project reports, periodic visits to the customer, and telephonic exchanges
B.Subordinates, project team members, and the project sponsor
C.One-time reports, weekly reports, and monthely reports
D.The telephone, facsimile, and data transmission

70题:

The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS
A. Schedule and cost                  
B. Organization structuring
C. Management coordination            
D. Quality of work

4题:以历史坐标轴观察,企业信息化是()。
A.生产关系的改变
B.劳动工具的技术进步
C.劳动者的替代
D.对传统生产工艺的摒弃
38题:关于范围管理相关的描述,不正确的是()。
A、范围管理计划描述了如何定义、制定、监督、控制和确认项目范围
B、范围管理计划可以是正式的,或者非正式的,可以是非常详细或高度概括的
C、需求管理计划描述如何分析、记录和管理需求
D、需求管理计划是编制范围管理计划的重要参考依据
35题:

项目经理对某软件开发流程中的“概要设计”活动进行历时估算时,参考了以往相关项目活动情况,他采用的是()方法
A、专家判断
B、类比估算
C、参数估算
D、三点估算