The( )provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B .contract
C.project human resource plan
D .project charter
软题库参考答案:D(仅供参考)
软题库解析:正在加载....
你可能感兴趣的试题
If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and( ) of the project management plan. Are revised and reissued to reflect the approved changes
A、developing baselines
B、testing baselines
C、schedule baselines
D、ending baselines