某项目的项目经理在进行项目范围变更时,在对项目的技术和管理文件做了必要的修改后,他下一步应该()。
A、及时通知项目干系人
B、修改公司的知识管理系统
C、获取客户的正式认可
D、获得政府认可
The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS
A. Schedule and cost
B. Organization structuring
C. Management coordination
D. Quality of work
A project life cycle is a collection of generally sequential project(1 )whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic (2 )for managing the project, regardless of the specific work involved.
(1)A. phases B. processes C. segments D. pieces
(2)
将路由器、交换机、网关、集线器、终端接入设备、有关系统软件等实施集成服务称为( )
A、网络集成实施服务
B、主机集成实施服务
C、智能建筑系统集成服务
D、应用系统集成服务