某系统集成公司据经验决定建立一套变更控制系统,为保证该系统行之有效,该系统中必须包括的内容是( )。
A.对每个项目的各条功能和物理特征作出的具体描述
B.项目预期的、具体的变更要求,以及响应计划
C.定义项目文档如何变更的程序和规则
D.预测项目变更的绩效报告
Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( ).
A.change the scope baseline
B.contact the customer to determine if the change adds value
C.call a meeting of the change control board
D.change the project's objectives
Categories of risk response are ( ).
A.Identification, quantification, response development, and response control
B.Marketing, technical, financial, and human
C.Avoidance, retention, control, and deflection
D.Avoidance, mitigation, acceptance, and Transferring