若一个项目由9个主要任务构成,其计划图(如下图所示)展示了任务之间的前后关系以及每个任务所需天数,该项目的关键路径是 (1) ,完成项目所需要的最短时间是 (2) 天。
(1)A、A→B→C→D→I
B、A→B→C→E→I
C、A→B→C→F→G→I
D、A→B→C→F→H→I
(2)A、16
B、17
C、18
D、19
软题库参考答案:A、D(仅供参考)
软题库解析:正在加载....
你可能感兴趣的试题
DOM is a platform- and language- (1) API that allows programs and scripts to dynamically access and update the content, structure and style of WWW documents(currently, definitions for HTML and XML documents are part of the specification). The document can be further processed and the results of that processing can be incorporated back into the presented (2) . DOM is a (3) -based AP1 to documents, which requires the whole document to be represented in (4) while process