In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication. According to Metcalfe’s Law, a project with 10 stakeholders has ( ) potential communication channels.
A、10
B、45
C、50
D、100
软题库参考答案:B(仅供参考)