Estimating schedule activity costs involves developing an(1 )of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of (2 )to facilitate comparisons both within and across projects. The(3 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.
(1)A. accuracy B. approximation C. specification D. summary
(2)A. activity B. work C. currency D. time
(3)A. project scope statement
B. statement of work
C. project management plan
D. project policy
软题库参考答案:B、C、A(仅供参考)
软题库解析:正在加载....
你可能感兴趣的试题
某公司从甲地向丁地运送物资,运送过程中先后需要经过乙、丙两个中转站,其中乙中转站可以选择乙1 和乙2 两个可选地点,丙中转站可以选择丙1、丙2 和丙3 三个可选地点,各相邻两地之间的距离如表所示,则甲地到丁地之间的最短距离为( )。
A、64
B、74
C、76
D、68
模块设计时通常以模块的低耦合为目标,下面给出的四项耦
完整内容请通过题库练习系统作答