下图是某项目成本风险的蒙特卡罗分析图。以下说法中不正确的是( )。
A.蒙特卡罗分析法也叫随机模拟法
B.该图用于风险分析时,可以支持定量分析
C.根据该图,41 万元完成的概率是12%,如果要达到75%的概率,需要增加5.57 万元作为应急储备
D.该图显示,用45万元的成本也可能完成计划
The work that needs to be accomplished to deliver a product, service ,or result with the specified features and functions is called ( ).
A、Scope management
B、Integrated management
C、SOW
D、PMO
在信息系统安全技术体系中,环境安全只要指中心机房的安全保护。以下不属于该体系环境安全内容的是( )。
A.设备防盗器
B.接地和防雷击
C.机房空调
D.防电磁泄漏
A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solutionat the meeting, The project manager should( ).
A.Tell the customer that he will not address any problems
B.Tell the customer that the problem is not sufficiently defined to company to a solution
C.Collect as much information on the problem without committing hiscompa