In project management , a ( 1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2 ) ,budget and duration, linked by dependencies and scheduled events.
(1)A. schedule
B. activity
某信息化建设项目的状态数据为:实际成本(AC)=44150元,计划值(PV)=40800元,挣值(EV)=36610元,则成本绩效指数是()
A、-7540
B、-4190
C、0.83
D、0.93