(  ) is a measure of schedule performance expressed as the difference between the earned value and the planned value.
A、 Schedule variance (SV)
B、 Cost variance (CV)
C、 Actual cost (AC)
D、 Earned value (EV)
查看答案

软题库参考答案:A(仅供参考)

软题库解析:正在加载....

你可能感兴趣的试题

32题:关于供应商项目内部立项的描述,不正确的是() 。
A、任何规模和类型的项目均要求进行内部立项
B、通过项目立项方式可以确定合理的项目绩效目标
C、通过项目立项方式可以分为项目分配资源
D、 以项目型工作方式,提升项目实施效率
51题:

在进行项目成本估算时,可以使用多种技术和工具,其中,()相对于其他估算技术来说,成本较低,耗时较少,但准确性也较低。
A、专家判断
B、类比估算
C、参数估算
D、三点估算

68题:(  )The capability provided to the consumer is to use provider’s applications running on a cloud infrasture. The applications are accessible from various client devices through either a thin client inface, such as a web browser(e.g.,erb-based E- mail),or aprogram interface.
A、laaS     
B、PaaS   
C、saaS    
D、DaaS
73题:()helps to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes.
A、checklist analysis
B、sensitively analysis
C、decision tree analysis
D、simulation

49题:

项目合同管理不包括( )。
A.合同签订
B.合同履行
C.合同纠纷仲裁
D.合同档案管理

13题:有两个类Apple和Tomato均继承父类Food,这三个类均实现了getTaste()方法,但Apple、getTaste()和Tomato。getTaste()的实现是完全不同的。这体现了面向对象的设计(00D)中的()。
A.封装
B.抽象
C.多态
D.接口