During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want&n
第57题: 李先生是某软件开发公司负责某项目的项目经理,该项目已经完成了前期的工作进入实现阶段,但用户提出要增加一项新的功能,李先生应该( )。
A、拒绝该变更
B、认为用户要求合理,立即实现该变更
C、通过变更控制过程管理该变更
D、要求用户与公司领导协商