In project management and systems engineering, (     ) is a deliverable-oriented breakdown of a project into smaller components. It is a key project deliverable that organizes the team's work into manageable sections.
A. RBS
B. PBS
C. GBS
D. WBS
查看答案

软题库参考答案:D(仅供参考)

软题库解析:正在加载....

你可能感兴趣的试题

72题:The IoT architecture can be divided into three layers.  (     ) is the key layer to realize the foundational capabilities which support the electronic devices interact with physical world.
A. Sensing layer
B. Network layer
C. Application layer
D. Operation layer
6题:统筹全国一体化政务服务平台建设和管理,加快地方政务服务业务系统与国家政务服务
平台的全面对接融合属于()。
A.G2G
C.G2B
D.G2C
B.G2E
21题:

要缩短关键路径,下列哪一方法对降低项目成本有最大
完整内容请通过题库练习系统作答
66题:

WLAN is increasingly popular because it enables cost-effective () among people and applications that were not possible in the past.
A.line    
B.circuit    
C.connection    
D.Interface

49题:

塔库曼的团队建设理论认为,项目团队建设的生命周期中不包括( )阶段。
A、形成(forming)
B、磨合(running)
C、震荡(storming)
D、规范(norming)

63题:

甲公司承担了某市政府门户网站建设项目,与该市信息中心签订了合同。在设计页面的过程中,经过多轮讨论和修改,页面在两周前终于得到了信息中心的认可,项目进入开发实施阶段。然而,信息中心本周提出,分管市领导看到页面设计后不是很满意,要求重新设计页面。但是,如果重新设计页面,可能会影响项目工期,无法保证网站按时上线。在这种情况下,项目经理最恰当的做法是( )。
A.坚持原设计方案,因为原页面已得到客户认可
B.让设计师加班加点,抓紧时间修改页面
C.向领导争取网站延期上线,重新设计页面
D.评估潜在的工期风险,再决定采取何种应对措施