On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and ( ) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development